I don't think this space even allows me enough room to tell the entire story from start to finish but I'll try to give a condensed version. Although our contract required Jaehne to obtain Builder's Liability insurance, he failed to do so for several months. By the time I discovered he had never purchased the required insurance, our concrete slab had already been poured and the house framing was partially done. Thus, his builder's liability insurance will not cover any problems related to those portions of the build and, now barely 18 months after moving into our new home, we are definitely having severe foundation problems. As the build progresses, it also became apparent that Jaehne had lied when he claimed that he had the financial ability to front at least $100,000 between draws. We gave him a check for $25000 early on that he CLAIMED was for a downpayment on our wnidow and door package because "it is a custom order and they want at least half before they'll even start making the windows and doors" and then on his first bank draw he claimed another $20,000 was to go to finish paying for the windows and doors. But, shortly after our windows and doors had been installed, we got hit with a lien for $54,000 from the window and door supplier. They had never been paid a single penny. Jaehne was never able to explain where the $45,000 that we gave him for the windows and doors had been spent. Instead, we wound up having to pay off the $54,000 lien because Jaehne claimed he was broke. I wanted to fire Jaehne at that point but our banker (Clay Ingram - First National Bastrop) convinced us that if we fired Jaehne our house would never get finished. So, we agreed to not fire Jaehne at that time but instead, Jaehne would submit bills from subcontractors and materialmen to us and we would have draw checks made out directly to the subs and materialmen. Once the house completely finished, if there was still any money left over, Jaehne would collect that as his profit. One would have thought since he no longer had to invest any of his own money in our build, Jaehne would have hurried to get our house finished so that he could collect his profit. All he had to do was keep scheduling work and supervising it and pass the bills on to me. Instead, from that point forward, he did almost no work at all on our house. The only major thing that was accomplished over the next three months was that the driveway was poured and we paid for both the materials and the labor for that job with draw checks directly to the subcontractors and suppliers. Nevertheless about three months months after agreeing to wait until the house was finished for his "profit," Jaehne started demanding that we give him another draw. We scheduled a meeting with Jaehne on Dec 26, 2008 at FNB -Bastrop to attempt to work thru the financial issues. The day before Christmas, a subcontractor (whom Jaehne had supposedly paid months before) called to tell us that Jaehne had given him a bad check for the $12,000 he was owed for work done on our house. The man's very pregnant wife met with us and Jaehne at FNB the day after Christmas and after Jaehne admitted to owing the money, we paid that contractor. At that point I tried to get a complete accounting but Jaehne would/could never provide proper documentation. Instead, he gave us a list he made up where he claimed HE had spent $269,000 building our house. But, the list included the $54,000 lien that WE had paid, plus another check for $500 written TO us to reimburse us for a change order that we decided not to do after all and his $500 check had bounced and he had never made it good! I insisted he had to back up the "list" with copies of canceled checks, invoices materials/supplies, and lien releases from subcontractors. Over the next 2 months, Jaehne fed us documents piecemeal. But an investigation into those documents he provided (by calling the subs/suppliers) showed that he had apparently used our money to pay debts arising from his previous business ventures; that he was attempting to double (and sometimes triple) bill us for the same work; that he was billing us for materials and supplies that were never used in our home (but apparently WERE used in a spec home he was building at the same time); that he had solicited false lien waivers; that he had paid sub-contractors with rubber checks; etc. etc. etc. This dishonest was the final straw. I fired him. But poor record-keeping and dishonesty were not the only issues we faced. Thoughout our build we also had issues with Jaehne's poor building practices... and his absolute refusal to honestly address those issues. Among other things: * Rather than reject concrete that had sat in the trucks too long before being discharged, Jaehne (or Jaehne?s agent and subcontractor, Bundage Pumping) authorized water to be added on-site to two out of eleven loads of concrete. Ten gallons of water was added to one load and thirty gallons of water was added to another load. Adding extra water to concrete decreases its strength. We did not learn of the watered concrete until we got copies of the concrete supplier's delivery records in early 2009. However, even as early as July 2008, a severe crack that developed across our screen porch area. It was wide enough then to stand a quarter upright but Jaehne claimed it was "just a surface crack". We also had issues with severe honeycombing around the perimeter of the slab - so bad in many places that the rebar was exposed. Jaehne was going to "fix that" at the end of the build. Now, two years after moving into our home, we have multiple severe cracks in our garage and porch areas and are having to spend thousdand of dollars in additional money to have the garage foundation stablized and then repair framing that has bowed out of true. * Jaehne totally ignored the fact that we wanted open-web joists between the two floors of our house so that HVAC ductwork could be kept within the heated/cooled envelope of the house. (There were two closets on the original plans to house the two HVAC units). Instead he used I-beam joists. Even after this discrepancy was pointed out to him before the second floor was framed, and he was told to "Before you frame the second floor, TALK TO AN ENGINEER and make sure that holes can be cut through those i-beams large enough to allow HVAC ducts to be run between the floors. If that is possible, you can keep the i-beams. Otherwise you need to replace them with open-web joists before you frame the second floor." Instead Jaehne rushed ahead and framed the second floor and the roof. Then when he was asked, "DID YOU TALK TO AN ENGINEER and get approval?" he responded, "trust me, it's not going to be a problem." What Jaehne meant by that was that he had unilaterally decided to move our two HVAC units to the attic (the worst possible location for AC units given Texas's hot summers) and build chases through our upstairs closets to run ductwork down to the first floor. His unilateral decision resulted in a veritable giant spiderweb of HVAC duct lines plus two huge HVAC units crowding our attic so, instead of the expansive storage area we expected, one can barely move around up there. Plus we lost a huge amount of closet space to chases. And, worst of all, we had to pay for larger HVAC units that must work harder to push air thru hundreds of feet of minimally insulated ductwork so, instead of an energy efficient home, we have outrageous cooling bills each summer and go through ridiculous amounts of propane whenever it gets cold in the winter. * Jaehne failed to properly install the Tyvek housewrap on our house. And they did so even after I contacted Dupont which sent their Residential Tyvek Specialist to my home to explain to Jaehne and his subs EXACTLY how to do it right and offered to make a second trip out to inspect and insure that the Tyvek wrap had been corrected. Jaehne was explicitly instructed not to install "a single piece of Hardie" until the Tyvek Specialist had come back to inspect. He ignored those explict orders and rapidly put up Hardie plank to cover over the improperly installed Tyvek instead of fixing it. After we fired Jaehne and took over finishing our home ourselves, we also discovered that the elevator shaft was framed about 6 inches too close to one edge of the house. This resulted in the attic headroom being a few inches too short for the elevator - so we had to pay over $10,000 to have a bumped up section of roof built to accomodate the elevator. When we started installing the flooring, we learned that the rough-in staircase was so poorly built that some steps were as much as 3/4th of an inch taller or shorter than others. This creates a tripping hazzard. We had to have the rough staircase pulled out and completely rebuilt before we could finish installing our hardwood floors. Before we had our insulation and sheetrock installed, we noticed that the windows had not been properly shimmed around the edges and, as a result were begining to bow to the point that one could see daylight between the window sash and window frames. We had to go back and properly shim all the windows. When the door supplier (remember the one Jaehne never paid) came to install handle-sets on our patio doors, one set of doors was so far out of allignment with each other that the handleset could not even be installed. We had to have that fixed as well. In total we have already spent close to $600,000 on this house and we have not done ANY upgrades. To keep costs down we did much of the work ourselves and we still haven't built the decks, put in any crown molding, or done any of the landscaping that was supposed to be included for the turn-key price of $519,000. And, Jaehne STILL has not released the lien he has against our property plus we have our attorney bills to pay. A TOTAL DISASTER. STEER CLEAR!
Description of Work: In May 2008, we hired Patrick Jaehne (d/b/a Jaehne Custom Homes) to build a 3200 sq ft, two-story, three bedroom custom home with a 900 sq ft semi-detached garage for us in Cedar Creek between Austin and Bastrop. Our contract price was $519,960. We owned the land free and clear before we hired Jaehne, so the price was JUST for building. We wound up firing Patrick in March 2009. The house was less than half-way completed and he had burned through nearly 60% of our total building budget - with NO UPGRADES or change orders. We fired him because numerous construction issues and ethical issues that eventually totally eroded our trust in his workmanship and in his business ethics. After we fired him, he refused to release a residual lien for $56,000 that he held against our property claiming that we still owed him money. This despite the fact that, before firing him, I had asked him for a complete accounting of where the monies he had been paid had been spent (so that we could determine if we owed him anything more and had told him that I would reimburse him for any out of pocket expense) he was unable/unwilling to provide an accounting. Ultimately we wound up having to file suit against him for fraud, fraud in the inducement, breach of contract, and conversion. As of this writing, our law suit is still pending in district court in Bastrop but it has been "stayed" (i.e., put on hold) because Jaehne has filed bankruptcy in an attempt to get out of paying his other debts including a judgment for over $300,000 that another of his clients won against him in a lawsuit that also included claims for fraud. Our lawsuit is a public record. You can look it up in the district court's records under Angel v. Jaehne. Patrick Jaehne's bankruptcy filing is also a public record. You can look that up in the Western District of Texas Bankruptcy Court in Austin. From the very beginning, our experience with Patrick Jaehne was a disaster. He lied to us before we even signed the contract. One of the questions I asked every potential builder that I interviewed was whether he or any company he owned had ever had a build go so bad that the homeowner either filed suit against him or - since so many construction contracts require mediation - the dispute had gone to mediation. Jaehne lied and said he had never been sued... except for his divorce. It was only later that we learned that there were TWO lawsuits pending against one of his companies at the time we were interviewing him. Both were filed in district court in Bastrop Texas. You can look them up. One is Lawrence v. S&J Endeavors and the other is Walden v. S&J Endeavors. Patrick Jaehne also has been successfully sued by unpaid suppliers (I forget the name but there are judgement liens against him on file in the Bastrop County land records.) and even by his own father. (Jaehne v. S&J Endeavors in Lee County.) And, I have lost count of the number of his former clients who have now told me that they wound up having to pay off liens against their property because Patrick Jaehne failed to pay this or that supplier or subcontractor or gave the supplier/subcontractor a bad check.
All statements concerning insurance, licenses, and bonds are informational only, and are self-reported. Since insurance, licenses and bonds can expire and can be cancelled, homeowners should always check such information for themselves. To find more licensing information for your state, visit our State Contractor License Requirements page.
*Contact business to see additional licenses.
Service Categories
Homebuilders,
Hauling
FAQ
S & J Endeavors LLC DBA S & J Homes is currently rated 1 overall out of 5.
No, S & J Endeavors LLC DBA S & J Homes does not offer free project estimates.
No, S & J Endeavors LLC DBA S & J Homes does not offer eco-friendly accreditations.
No, S & J Endeavors LLC DBA S & J Homes does not offer a senior discount.
No, S & J Endeavors LLC DBA S & J Homes does not offer emergency services.
No, S & J Endeavors LLC DBA S & J Homes does not offer warranties.